Lake Turkana ready to inject 33 percent of the agreed power into the national grid

Lake Turkana ready to inject 33 percent of the agreed power into the national grid

 

Lake Turkana ready to inject 33 percent of the agreed power into the national grid


Lake Turkana Wind Power is currently in a position to produce up to 33 percent of its expected target of 310 MW. In addition a total of 347 out of 365 turbines have already been already erected, which is a clear indication that the project is on course for completion as per its original plan by June this year.
The firm’s General Manager, Phylip Leferink, said the remaining twenty turbines have already been delivered on site and the technical team, from Vestas and Siemens, are working day and night to ensure that they meet the timelines as per the contractual obligations. Assembly of the turbines began in March 2016 and all 365 are expected to be up and running by June 2017.
The total cost of the project is estimated at Kes 70 billion, said Mr Leferink, adding that the firm targets to have an annual generation capacity of 1.6 billion kilowatt hour (kWh), while the tariff rate would be KES 8.6 per kWh as per the 20-year long deal struck between the wind farm and the government.
A double circuit 400kV, 438km transmission line is currently being constructed by Kenya Electricity Transmission Company (Ketraco). The line will evacuate the electricity from the 40,000-acre wind farm to the national grid via the Suswa sub-station.
On completion, the Marsabit-based wind firm, which is arguably the biggest wind farm on the continent, will produce enough energy to power an additional 1 million Kenyan households.
Once Lake Turkana Wind Power is fully operational it will add 310 MW of renewable generation capacity to Kenya’s grid. Currently Kenya, which relies heavily on renewables such as geothermal and hydro-power, aims to expand installed capacity to about 6,700 MW by 2017, up from 1,700 MW in 2013.

CONTACTS

+254 (0)20 221 3493

NEWS & MEDIA
media@ltwp.co.ke

OTHER QUERIES
info@ltwp.co.ke

Lake Turkana Wind Power Ltd
P.O Box 2114 - 00502
Karen, Nairobi
Kenya

Copyright © Lake Turkana Wind Power 2015. All Rights Reserved

ENHANCING EMPLOYABILITY

 

This pillar focuses on access to education and development of skills for the labor market. In 2015, WoC provided books and pens to 18 primary schools. WOC also distributed 500 desks to 23 primary in South Horr, Arge, Mercy, Namarei, El Molo bay and other parts of Laisamis constituency.

 

WoC has identified the extension of Sarima School, the construction of facilities at Nyiro boys and Nyiro Girls School as key focus areas for the education pillar in 2016. WoC will also continue to support the provision of teaching materials to local primary schools.

 

WoC is in discussions with the Marsabit South Technical Institute to determine the nature and type of investments it can make to support development of vocational skills in Laisamis. This is expected to boost tertiary education as well as enhance future employability in the area. This project will be launched during the operational phase of the wind farm.

 

WoC is also planning to set up a scholarship fund for secondary and vocational education in the area.

×

ENHANCING ACCESS TO HEALTH

 

The expansive but sparsely populated project area, coupled with years of under-investment in the sector has resulted in limited access to health services by the local communities. WoC support to health focusses on enhancing access to health services by upgrading physical infrastructure and during operation of the windfarm, partnering with stakeholders to support targeted outreach programs.

 

WoC has supported the improvement of health facilities at Burri-Aramia dispensary (solar lighting, vaccine freezer, shelving for medical supplies and furniture including examination ward and delivery beds and patient toilets among other items.)

 

WoC has also contracted a local organization – Community Empowerment Development Initiative Marsabit (CEDIM) to undertake HIV/AIDS sensitization campaigns. CEDIM has trained 17 Community Health Workers (CHWs) and attached them to existing government run health facilities to sensitize and educate the local population on matters around HIV/AIDS. In2015, WoC carried out a three-month HIV/AIDS awareness and testing campaign in around the wind farm site.

 

In future, WoC plans to support Marsabit County in the upgrading of facilities at Laisamis health centre and other health centres in the area.

×

PROVIDING WATER

 

Due to the arid nature of Marsabit, water is a scarce commodity. LTWP has spearheaded the rehabilitation of several water boreholes and water supply points. The water points that have been rehabilitated include; Arge, Laga el fereji, Namarei, Kutider-Korr, Gatab III and El Molo.

 

WoC has installed a solar driven reverse osmosis system in Sarima village. In addition, WoC has built watering troughs in different parts of the constituency, to ease provision of water to livestock. There were no reported livestock deaths due to droughts in 2015 following construction of watering troughs in the dry season grazing area around Gatab.

 

WoC has also installed solar driven pumps to rehabilitated boreholes that had pump problems. On completion of the LTWP’s construction phase, 11 boreholes will be handed over to the community.

 

In 2016 WoC plans to build a 100,000 litre storage tank at Gatab III to ensure that there is adequate supply of water to the community and their livestock during periods of drought. WoC will also lay a 7-km water pipeline in Arge, to bring potable water to two villages of over 3,000 people in Arge.

×

OTHER COMMUNITY ACTIVITIES

 

WoC has rolled out a road safety campaign along the recently upgraded C77 public road between Laisamis and Sarima. CEDIM is the local partner implementing this activity, and they have already recruited and trained 12 people from centers and villages along the Laisamis-Sarima road to act as road safety educators.

 

In support of peaceful and secure communities, WoC has built accommodation for the Administration Police and extended the existing Police office in Loiyangalani.

×
×